Construction Archive

Welcome to the Construction Archive!

Here you can take a look back at the construction coverage TowersTimes provided of The Smiler. You can also view our timeline by clicking here.

Construction Update: May 14th 2013

Today we take a look at The Smiler as we race towards the opening date of May 23rd. Ground work is nearly complete with full landscaping now underway. The Marmaliser is receiving finishing touches to its theming and testing of the ride is continuing.

 

Construction Update: April 24th 2013

With The Smiler track being completed earlier today we immediately dispatched MI7 to bring you an exclusive first look from the air.

This is not the end, TowersTimes will continue to bring you the latest and greatest updates right up to and beyond the opening of the ride in late May.

 

Construction Update: April 13th 2013

Today saw the installation of a major new component – the support structure for the vertical lift hill. We’ve also taken a look at the rest of the site including The Marmaliser theming element which is nearing completion.

 

Construction Update: April 6th 2013

We’ve been back in the air again and we’re pleased to present the photos from todays flight. We also take a closer look at The Marmaliser, Station work and an amazing looking bunny hop from on the ground.

 

Construction Update: March 16th 2013

TowersTimes is pleased to present an on-ground update from the Construction Site. Today was the theme park opening day for 2013, so we took a few up-close and personal photos.

 

Aerial Update: March 12th 2013

TowersTimes is pleased to present what could be our last aerial update before the start of the season, In this update you can see work is continuing on the track with another corkscrew now in place since our last update. In addition The Smiler’s logo has replaced the Fanta one located at the bottom of Oblivions drop, the theming piece has started to go in on X Sectors central island. Lastly, the middle part of The Marmaliser has appeared on the construction site.

High quality versions of these images will be posted to TowersTimes Forum tomorrow.

 

Aerial Update: March 3rd 2013

Track work has started to pick up with the installation of further elements. Landscaping has begun on the surrounding area with fencing and paving going in.

 

Aerial Update: February 27th 2013

With groundwork nearly complete track installation is now progressing at a much faster pace. In this update you can see the brake run has been installed along with the airgates in the ride station.

 

Aerial Update: February 21st 2013

Progress on ground work has picked up with the majority of the footers and concrete now in place. The station framework is also nearing completion. The track near the top of the site above the toilets has also started to be installed. We also have a first look at ‘the marmaliser’ theming element.

 

Aerial Update: February 15th 2013

Not much time has passed since our previous update but we couldn’t wait to show you the latest progress on the construction site. Whilst there hasn’t been any visible track installation we have a large amount of progress with concrete pouring and footer installation.

As per our previous updates we have spoken to Alton Towers Resort and we have agreed to obscure parts of the ride as requested by the resorts marketing department. Sorry for this but it will be worth keeping any secrets safe until the ride is open

 

Track Delivery: February 12th 2013

An unusual section of track has arrived!

 

Aerial Update: February 8th 2013

It has been a few weeks since our last update due to weather conditions, however we’re back in the sky once again. Construction has progressed with considerable work on the footers of the ride, extending up to the top of X Sector. The repaint of Oblivion is also underway as you can see in these photos.

We have spoken to Alton Towers Resort and we have agreed to obscure parts of the ride as requested by the resorts marketing department. Sorry for this but it will be worth keeping any secrets safe until the ride is open!

 

Aerial Update: January 17th 2013

Whilst it has only been a few days since our last update we wanted to share some aerial photos of The Smiler in the snow.

We have also spoken to Alton Towers Resort and we have agreed to obscure parts of the ride as requested by the resorts marketing department. Sorry for this but it will be worth keeping any secrets safe until the ride is open!

 

Aerial Update: January 13th 2013

In our first full aerial update of 2013 we can see that track work is coming on very fast with the ‘Staffordshire Knot’ element completed. Work on the station and rest of the site is also progressing.

We have also spoken to Alton Towers Resort and we have agreed to obscure parts of the ride as requested by the resorts marketing department. Sorry for this but it will be worth keeping any secrets safe until the ride is open!

 

Aerial Update: January 6th 2013

In this bonus photo we can see that track and station work is progressing.

 

Track Update: January 3rd 2013

Our first update of the new year shows some unusually shaped support structures as well as track and supporting equipment for the continuing construction.

 

Construction Update: December 31st 2012

A ground level view of The Smiler construction site.

 

Track/Theming Update: December 23rd 2012

Another update featuring a look at a potential The Smiler theming element.

 

Track Delivery: December 8th 2012

Another delivery of what appears to be the break run

 

Track Delivery: December 5th 2012

A delivery of track and station material

 

The Smiler From The Air: December 5th 2012

A birds eye view of The Smiler construction site, as groundwork continues.

 

Track Delivery: November 23rd 2012

A small update today showing another delivery of track

 

The Smiler From The Air November 21st 2012

Exclusive to TowersTimes, a birds eye view of the latest track delivery and The Smiler construction site, as groundwork continues.

PLEASE NOTE: These images are exclusive to TowersTimes and must NOT be copied or replicated in anyway without our prior consent.

 

Track Delivery: November 15th 2012

More track has been delivered to the Resort during closed season…

 

Track Delivery: November 6th 2012

More track and ride parts have arrived on the Resort…

 

The Smiler From The Air November 3rd 2012

Exclusive to Towers Times, a birds eye view of The Smiler construction site. This will be a regular feature throughout the closed season so keep an eye on our forums and Facebook page for updates.

PLEASE NOTE: These images are exclusive to TowersTimes and must NOT be copied or replicated in anyway without our prior consent.

 

Track Delivery & Update: November 2nd 2012

More new track has arrived on the Resort and here is how the construction site currently looks.

 

Track Delivery: November 1st 2012

Another update from where the track is currently being stored at the Alton Towers resort.

 

Track Delivery: October 31st 2012

Track arriving on a daily basis at the Alton Towers resort.

 

Track Delivery: October 29th 2012

More track has arrive at the Alton Towers resort.

 

Track Delivery: October 27th 2012

Track has started to arrive at the Alton Towers resort. Thanks to Paul Jones who provided us with these images.

 

Track Delivery: October 27th 2012

Track has started to arrive at the Alton Towers resort. Thanks to tharrison4815 on our forums for these photos.

 

Construction Update: October 27th 2012

Construction continues. Thanks to Paul Jones who provided us with these images.

 

Construction Update: October 22nd 2012

Construction is progressing with extensive work on the large pit that has been dug out. Concrete retaining walls are also being installed. Supports and track are now expected on site after the season ends.

 

Construction Update: October 4th 2012

Marketing has gone into full swing as the season is approaching its end. Banners have been updated across the park and construction is moving ahead with a very large hole appearing.

 

Construction Update: September 19th 2012

Groundwork is advancing as closed season approaches.

 

Construction Update: August 25th 2012

The Construction walls have been pushed further back to allow more area construction to commence.

 

Construction Update: August 11th 2012

Deep holes have appeared around the construction site, in line with the plans. We anticipate the first footers to be installed shortly.

 

Construction Update: July 15th 2012

 

Construction Update: July 1st 2012

 

Construction Update: June 24th 2012

 

Construction Update: June 16th 2012

 

Construction Update: May 27th 2012

 

Construction Update: May 20th 2012

 

Construction Update: May 12th 2012

 

Construction Update: May 9th 2012

 

Construction Update: May 6th 2012

 