Construction – 30th August 2017

These images, taken by a TTSP Community Member, show that track work is underway on the first drop and on the turns which have already been constructed, whilst next to the theming structure, the small building has now had basic walls and a roof added. Wooden fencing is also being added in an area towards the centre of the site. Inside the pre-show building, what appear to be studs have been added for the walls. Work is also underway on the first sections of the ride’s queue line with brick paving being laid at the Mutiny Bay end of the area.